Emergency maintenance - Reload of Manchester routers
Scheduled Maintenance Report for Simwood
Completed
The scheduled maintenance has been completed.
Posted Feb 18, 2016 - 22:08 UTC
Verifying
Both routers were reloaded successfully and the reload successfully corrected OSPF issues. We will not be proceeding with an upgrade at this time so whilst we will be making further checks now, this maintenance should be concluded.
Posted Feb 18, 2016 - 21:40 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 18, 2016 - 21:15 UTC
Scheduled
Following yesterday's issues in Manchester we will be performing a reload of both routers in Manchester this evening. We will perform this sequentially and reroute traffic where possible to minimise impact but, given the background to this, we cannot entirely rule out disruption.

A straightforward reload should take no longer than 5 minutes for each of the two routers but we are extending the window in case of any problems. Assuming the standard reload is successful, we may also proceed with a firmware upgrade to address the suspected OSPF bug.
Posted Feb 18, 2016 - 08:23 UTC